UPS Sizing & Runtime

Size an Uninterruptible Power Supply for critical loads and calculate backup runtime from battery capacity.

Units:
in LinkedIn
💡Size UPS at 60-80% of rated kVA to allow for crest factor and future growth. Online double-conversion UPS: 90-95% efficient. Always verify battery replacement cycle (typically 3-5 years for VRLA).
kVA_UPS = kW_load / (PF x eta) | t = (C_Ah x V_bat x eta_inv) / (P_load x 1000) x 60
UPS battery AC IN AC OUT t = C_Ah x V x eta / P_load
Input
Critical load iTotal power of loads that must be backed up in kW.
kW
Load power factor iServers/IT: 0.9-0.99. Mixed loads: 0.7-0.85.
UPS efficiency iOnline double-conversion: 88-96%. Line-interactive: 95-99%.
%
Battery string voltage iTotal battery string voltage. Typical: 96V, 144V, 192V, 240V DC.
V
Battery capacity iBattery capacity in Ah at C10 rate.
Ah
Inverter efficiency iDC to AC conversion efficiency. Typical: 88-96%.
%
Result
Required UPS size [kVA]
Recommended UPS (70% load) [kVA]
Backup runtime [min]
Battery energy [kWh]